Change Order Extends Burma Road Overlay; Contract Increases to $1.163m

October 29, 2025 County Commission
Change Order Extends Burma Road Overlay; Contract Increases to $1.163m

The Saline County Commission approved a change order to extend the Burma Road asphalt overlay 1.36 miles, from 0.5 miles north of Hedberg Road to 0.85 miles north of Falun Road.

The scope includes a 2-inch hot-mix asphalt overlay matching the existing cross slope, a 2-inch overlay on Falun Road approaches, milling of approach pavement to tie into the existing surface, and a 30-foot milled butt joint at the south end.


According to the change order estimate, added work totals approximately $300,000. Line items include 2,529.6 tons of commercial-grade HMA (Class A) at $110.95/ton, 240 square yards of profile milling at $2.26/sq yd, and 400 tons of AS1 aggregate shoulder at $47/ton. With the increase, the contract value rises from $863,129.90 to $1,163,129.90.


The Road & Bridge Department set a target completion date of November 15, 2025, weather and contractor scheduling permitting. The project is part of the county’s ongoing pavement maintenance and roadway safety program.


Share this story
Verified Organization Program
$99/year annual membership

We publish your events, job listings, and stories for you on a consistent schedule. You can still post yourself anytime, but you do not have to.

  • Done-for-you publishing on a consistent schedule: we handle your events, job listings, and stories for you.
  • You can still create your own events, jobs, or stories anytime, but you do not have to manage the workload yourself.
  • Monthly business outreach: just reply with bullets, photos, flyers, or links and we turn it into draft content.
  • Unlimited job postings - we can publish them for you, or you can post them yourself any time.
  • Unlimited Featured Events (normally $5/day) - we can publish and distribute them for you before the event.
  • Local SEO Package - we'll assist your site in optimizing for local search so you're found before your competitors
  • Priority placement in the category search for the Best In Salina directory
Learn About Verified
Salina311

Sign In