Salina commission to consider license agreements for canopy over Blue Skye Brewery sidewalk dining area
The Salina City Commission on Monday will consider two license agreements that would let Blue Skye Brewery and Eats, LLC build a permanent steel canopy over its sidewalk dining area on Santa Fe Avenue and correct the recorded size of that area, according to the commission packet.
One agreement would amend the restaurant's sidewalk cafe license. The other would allow permanent support columns and concrete footings in the city's Santa Fe Avenue right-of-way, according to a staff report from Margy Clem, deputy director of community and development services.
Background
The commission approved the original sidewalk cafe agreement in May 2018, and the Business Improvement District No. 1 Design Review Board approved a canopy design that year and changes to it in 2019, according to the staff report. The dining area and storefront work were built, but the canopy never was.
When the business applied for a building permit for the canopy in 2026, staff found two differences from the approved plans, according to the report. The dining area was built 6 feet deep by 22 feet, 5 5/8 inches long, about 134.8 square feet, instead of the licensed 6 feet by 20 feet, 9 inches, about 124.5 square feet. And the canopy design had been changed to use permanent load-bearing steel columns on concrete footings in the right-of-way.
The amended license would match the existing dining area. No expansion or change in location is proposed, according to staff. The corrected area remains under the 200-square-foot maximum in city code and leaves about 10 feet, 6 inches between the railing and the curb, more than the six-foot pedestrian path the city requires, the report says.
The canopy
The proposed canopy would extend about 6 feet from the building and span the length of the dining area, with a steel frame and angled steel shade fins painted black to match the existing railing and at least 8 feet of clearance above the sidewalk, according to the report.
It would rest on six load-bearing steel columns attached to concrete footings about 3 feet below the sidewalk. Four columns would replace existing railing posts, and two would be next to the building. According to the applicant, engineers found that supporting the canopy entirely from the building would require extensive investigation and changes to the existing structure, the report says. The columns would be bolted to the footings so the canopy could be removed later without demolishing the footings or sidewalk.
The Design Review Board voted 3-0 on Oct. 22 to recommend the amended sidewalk cafe license and 3-0 to approve a certificate of compatibility for the canopy, according to the report. Because the columns and footings are permanent structures in public right-of-way, the separate license agreement requires commission approval.
The work would be built and maintained at the applicant's expense, with no city funding, according to the fiscal note. Staff recommends approval of both agreements.
The commission meets at 4 p.m. Monday, Nov. 23, in Room 107 of the City-County Building, 300 W. Ash St. The meeting is also available on Zoom and on the city's YouTube channel, according to the agenda.