KDOT plans temporary K-4 crossovers around Southeast of Saline while school entrance design is revisited

November 24, 2026 government, public meetings, USD 306, Southeast of Saline, school board, KDOT, K-4, Gypsum, road construction, school entrance, traffic
KDOT plans temporary K-4 crossovers around Southeast of Saline while school entrance design is revisited

The Kansas Department of Transportation plans to build temporary crossovers on K-4 east and west of Southeast of Saline so highway construction can continue while the agency and the district work out a revised design for the school's entrance, KDOT officials told the USD 306 Board of Education on Monday.

The board held a special meeting to hear the presentation from Deputy Secretary and State Transportation Engineer Greg Schieber and Area Engineer Karlton Place of KDOT's Ellsworth office. The board took no action on the plan.

Schieber said that about 1,500 to 2,000 feet west of the school, traffic on the new alignment would cross over to existing K-4, pass the school's main entrance as it is used now, and return to the new alignment just past Cunningham Road, about 3,000 feet east of the school. Traffic would use about 5,000 feet of existing K-4 in front of the school. The crossovers would be paved and maintained through the winter, including snow removal.

Schieber said the arrangement lets the contractor demolish sections of existing K-4 and extend box culverts outside that stretch. KDOT will not work on the new alignment in front of the school until the entrance grade and any raise of the new roadway are resolved, and the crossovers would stay in place through the end of the school year. Construction on the main entrance would not happen until after the school year ends.

Schieber said KDOT wanted to explain the plan in person because of earlier communication problems, so the public would not see crews working and assume the agency had settled on an entrance design without the district. Earlier this month, the board voted 6-0 to oppose KDOT's entrance plan as it was presented at the time.

Schieber said the contractor could be ready to start work on the crossover areas the week after Thanksgiving, around Nov. 30, depending on how quickly KDOT gets transition details to the contractor and on weather for asphalt paving. KDOT plans to send a written update describing the plan this week.

KDOT proposed posting the crossover transitions and the stretch of existing K-4 at 35 mph. The highway is now posted at 55 mph with a flashing 45 mph school zone, and KDOT officials said that with a 35 mph limit they would likely remove the flashing beacon assemblies to avoid confusion. Board members said they were comfortable with 35 mph.

On the entrance itself, KDOT officials said they are evaluating options that would bring the grade to about 3%, with a 40-foot leveling pad where vehicles would wait at the highway. Board members said they expect KDOT to return to the board's December meeting with the revised entrance proposal.

KDOT officials also said the contractor still plans to take down the temporary signals and open the river bridge by Thanksgiving, and that flaggers and one-way traffic will be used at times while the crossover connections are built.


Share this story
Printed for Salina

Get the newspaper or the Monthly Almanac

The newspaper

Weekly print edition

The week in Salina, on paper. Local stories, events, and where your neighbors stand.

Salina311 newspaper
$21.45/mo
Delivered every Sunday · $257.40/yr
Get the newspaper
Not a newspaper

The Monthly Almanac

A 32-page record of last month, the numbers that matter, and the month ahead.

Monthly Almanac
$10.70/mo
Delivered at the beginning of each month · $128.40/yr
Get the Monthly Almanac
Salina311

Sign In